Building of the depot basement is ongoing. The depot will from wood, so we used a blocks of sacrificial formwork.
Concreting of depot basementfrom a blocks of sacrificialformwork. (photo © Tomas Randysek)
Basement of the station building. (photo © Tomas Randysek)
View on the building site. (photo © Tomas Randysek)
Baseplates of the station building and workshop were concreted. Building of depot basement continued gradually.
Baseplate of the station building. (photo © Tomas Randysek)
Baseplate of the workshop. (photo © Tomas Randysek)
Building of the depot. (photo © Tomas Randysek)
A soil after basement excavation. (photo © Tomas Randysek)
An remaining switch-points machines has been installed.
Jirka is installed switch-pointsmachine. (photo © Tomas Randysek)
Installed switch-point machines. (photo © Tomas Randysek)
We moved bricks material from buffer stock too. The basement is concreted so that Jano and Stefan will build enclosures walls by and by.
Bricks movement. (photo © Tomas Randysek)
A previous rainy season slacked up building works. The basement of depot is completed, the floor is graveled ant track were laid. Jano and Stefan put down isolation this day. They delivered wood for depot and ceiling beams for station building.
A gravel floor ... (photo © Tomas Randysek)
... and track in the depot. (photo © Tomas Randysek)
An isolation laying. (photo © Tomas Randysek)
A building material of the depot. (photo © Tomas Randysek)
Unloading of the ceiling beams. (photo © Tomas Randysek)
We started with building of the depot and the station building.
The building of depot in progress. (photo © Tomas Randysek)
The building of station building in progress. (photo © Tomas Randysek)