Number of visitors:


Events:

Optimized for browser:

Lokality návštěvníků našich stránek

You can see more detailed information about the park railway execution in shopping and breathing centre Olympia Brno.



22th December 2011 - building operations on the round-house proceeded last month. Perimeter walls were build on the foundations and roof-frame was build on the perimeter walls.

26th November 2011 - lining of the round-house undeground part was completed including concreting of the formwork blocks sheeting. The bricking of an aboveground of the round-house started.

10th November 2011 - the workshop penthouse was completed. Building of the round-house is continuing. Isolation of foundations is gluing and underground part is bricking concretelly.

19th October 2011 - the south wall of workshop got a new fasade plaster. Carpentry Lubomir Plachy is continuing with building of a workshop penthouse. But especially, the first twelve cubic metres for round-house was poured from a mixer truck.

14th October 2011 - company of Lubomir Plachy started with building of the first platform eaves. Excavation of the round-house foundations is continuing. We moved some tons of rails and switches at the main station and we tried a new warning cross.

21th September 2011 - we started with concreting of curbs between entrance track and station building and we are concreting of pillars footing of the covered platform too. Company Elektro Fiala is installing lightning conductors on the all buildings. First cubic metres of the round-house foundations were excavated. The station building is getting an external isolation Ytong Multipor.

15th September 2011 - the track gave way under force vehicles during yearlong operation above all in curves. It was necessary fill up these places with new ballast. We used our two dump cars for the first time. These cars were loaded by ballast fraction 16/32 and they were coupled to locotractor and transported at incriminated places.

25th August 2011 - we have to lay an entry station track with a switch into depot for planned "Open day". Construction of the retaining wall is continuing. Company Bofa-mont started with assembly of fence on entry and departure lead. And we can transport earth eventually - the weather turned fine.

5th August 2011 - a system for waste water accumulation was completed. But concreting of crossings and welding of the both gridirons started mainly. Company Trasko is paving an entrace pavement.

1st August 2011 - the second voluntary job was under the direction our young people. Jano and Pista were on well-earned holiday and our boys offered to help us. Chief site manager Jiri planned to them some excavation work and retaining wall building as a reward. And some cleaning too.

30th June 2011 - the earthwork are continuing. Outdoor electric and water distributions were finished. Sewerage distributions are continuing too.

10th June 2011 - a ground shaping and excavation work ongoing on the building site. An excavator is buldozing an elevation and it is transporting unnecessary soil at the round-house provisionally. We had to carried out excavation work by construction machinery because a bedrock was very hard. But this will faster.

28th May 2011 - we are finishing work at the workshop. There is a landing above its part, which will use for an occasional overnight accomodation. The floor is from concrete pavement. The electric wiring is complete too.

23th April 2011 - the first voluntary work at Park railway Olympia. We executed excavation work around station building and we painted windows at workshop and depot.

21th April 2011 - building activity is high. The workshop is getting indoor and outdoor plaster. The roof on station building is completed. The depot has an outdoor plaster too. Company Slavona stacked an entrance door of the workshop and station building.

25th March 2011 - the spring arrived in Brno finally and intensity of building activity strongly increased. Electric wiring installation was completed in the station building and workshop. Interior walls of the station building were smooth out by leno weave fabric. There were put a tracks in the workshop. There were concreted floor in the station building. The roof of the workshop is getting a shingle cover.

28th January 2011 - old year tumbled over into new year and our building activity started again. The station building and part of the workshop got a new wooden windows. The roof of station building was completely cover with battens. Electric wiring and water installation are processing indoors.

15th December 2010 - last building works are ongoing before Christmas. Air temperatures is below freezing point still. Company Carpentry - joinery Plachy Lubomir is completing roofing of the main station. Walling of a separating walls is ongoing inside.

9th December 2010 - the building activity moved onto station building. The building of trusses and gables is ongoing. A part of a station building was weather-strip by plastic film and tarp so as we work in interior during frosty days.

4th December 2010 - a veritable winter reached into the south Moravia. This year any earlier than in last years. It will have an effect on ongoing building works. But we have roofed-in workshop before the first snow cower. Building of roofs of the station building ongoing.

21th November 2010 - the rainy ang foggy days are coming. A roof building of the workshop is finishing. The workshop entry gate was installed too. A rims of the station building are concreting. We are waiting a first frost and snow during the next week so we must cover in both buildings so we can move our works in the interiors.

4th november 2010 - a new photos of building were added. The wooden construction of depot is just before a completion. The enclosure walls of the workshop are built, a rim was concreted and a root frame is preparing. The station buildig grew out too, we moved a ceiling beams on the enclosure wals.

7th October 2010 - a new photos from building of the railway station were added. Basement of the station building, workshop and depot were concreted during last two months. We began building of the depot and station building.

3th August 2010 - we began concrete of buildings basement - basement of the workshop at the first. We must cleaned up hollow groves several times, because every rain scoured a clay back. The container and site barrack has been moved into building area too.

15th July 2010 - we gradually start to works on the main station. Area of the main station was fenced. Site excavation of depot, station building and workshop started too. Ytong bricks were delivered into buffer stock PASO a.s. Workers of Velecky company made provisional branch from track before a bridge into container, for easier manipulation with vehicles.

24th June 2010 - built-up of the main station is coming soon and we have to prepare necessary storage area.

10th June 2010 - company OK Mont completed track laying to main station. The most interesting part of the line got live contour. The train will travel through a bridge under the in-line skating rink, it will circle a hill with wooden labyrinth and it will chop out on the wayside station ...

20th May 2010 - a press conference on the occasion of the biocentre inauguration.

14th May 2010 - we planned a demonstration runs with steam engines for Olympia management and other concerned parties which are participate in the biocentre building.

12th May 2010 - the next photos from building of the biocentre were provided towards evening 12th May. A working activity on that day already desisted and you can see that all the arrangements are made for inauguration of the biocentre.

3rd May 2010 - the first test runs with a steam engine eventualized. The steam engine can put forth to double speed compared to battery engine. We wanted readiness of track for service.

27th April 2010 - a next inspection was on Tuesday 27th April. OK Mont´s workers reinforced rails joints and they repaired longitudinal deformations too. A driving properties markedly improved.

17th April 2010 - we must postpone a test runs on the first section regarding the bad weather. All week it was raining perseveringly and the biocentre was one mud. We made oneself understood on Saturday when was a nice spring sunny day. S.M.P.D., OK Mont and Velecky participated on a test runs.

8th April 2010 - a track laying continued from the last week on the building site.

1st April 2010 - a control day was at the building site on Thursday 1st April. The first meters of track were laid into the prepared gravel ballast. The bottom part of a track corpus is from ballast of 16-32mm fraction, the top part is from ballast of 8-16mm fraction. The ballast is from the stone pit Zelesice.

23th March 2010 - a spring is coming in these days and work on park railway started fully. You can see following photos, which capture situation from 23th March 2010.

11th March 2010 - the first switch prototype is almost finished and we have to try passability of all our bogies.

24th February 2010 - situation on building site will documented after some time. Wood species and elements for visitors activities were installed.

19th February 2010 - company Velecky started producing of the rails and switches for Park Railway Olympia.

8th February 2010 - we delivered 16 tonns rolling U section for rails and switches into company Velecky in Krenovice u Slavkova.

3rd November 2009 - when we traced out last stages, the weather was very bad. It was heavily snowing from early morning and traffic calamity was in all town. In site was much of slush. But we have to abide with building harmonogram.

24th October 2009 - we met on 24th October so that range and lay out curves between tunnel and retaining station. We started to work our first brigade hours.

19th October 2009 - colleague Roman Siler provided next photos of the biocentre building.

29th September 2009 - we caught first photos from building site in the late September. Ground shaping proceeded on building site at the moment. Excavators and goods vehicles moved a tons of earth and they created hills and pits in bio-centre. Bulldozers and road graders gradually sleeked terrain. Building of the bridge started, by which railway will pass under the in-line skating rink.